Gravesham, in numbers

Projects: Gravesham

Gravesham local authority area. Every figure carries its own date.

The local plans, investments and decisions worth following.

4 selected records checked against official sources. A plan is not a completed project; each record shows the stage its source establishes.

St Alban’s Close, Gravesend

SoloHaus homes for single residents

Purpose-built modular homes have been handed over to the council.

Eight homes handed over July 2026; occupancy not verified · evidence dated 2026-07-23

Responsible body: Gravesham Borough Council and The Hill Group

What the source says: The announcement confirms completed accommodation for single people who have experienced homelessness. It does not report long-term housing outcomes.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

SoloHaus homes handed over →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Support residents after the SoloHaus handover →

Make room for homes people can afford →

Target support where disadvantages overlap →

How to track delivery →

Milton Place, Gravesend

Milton Place homes and public space

Building work has begun on homes with different tenures and support needs.

Construction underway July 2026 · evidence dated 2026-07-21

Responsible body: Gravesham Community Investment Partnership

What the source says: The 76-home scheme includes affordable rent, supported living, accessible homes and private-sale family homes. The whole total is not social housing.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Work begins at Milton Place →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Match Milton Place’s homes to different needs →

Make room for homes people can afford →

Target support where disadvantages overlap →

How to track delivery →

St Columba’s Close, Gravesend

St Columba’s Close council homes

A council development provides a mix of flats, maisonettes and houses.

Under construction; the autumn 2026 completion date remains a forecast · source does not state a status date

Responsible body: Gravesham Borough Council

What the source says: The page contains differing summer and autumn forecasts. Neither establishes completion; the reviewed stage remains onsite.

Next thing to establish: What dated decision or progress report confirms the current stage?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

St Columba’s Close construction update →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • What is the approved cost, including ongoing maintenance?
  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Keep construction forecasts separate from available homes →

Make room for homes people can afford →

Target support where disadvantages overlap →

How to track delivery →

Cascades Leisure Centre, Gravesend

Cascades Leisure Centre replacement

The council is preparing the site for the main construction phase.

Preparation works scheduled from 3 August 2026; main building completion not established · evidence dated 2026-07-31

Responsible body: Gravesham Borough Council

What the source says: Temporary parking, walking routes, bus-stop relocation and field closure are described separately from the future leisure facility.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Cascades site-preparation update →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?